9
Operational Projects
54.57
Total Capacity (kW) across 11 projects
78,899
kWh generated to date
Explore Our Current Cohort!
kWh generated to date
79,418.656
kWh total generated to date between the two cohorts
kWh generated to date per cohort
CO2 avoided
Where you build matters as much as what you build.
Location determines how much carbon each kilowatt-hour actually avoids.
22.96
CO2 avoided to date (tons)
How our capacity breaks down
From a single cohort to two, our installed capacity keeps growing, and so does the range of communities we reach.
Capacity split
Project type breakdown
45.57 kW
installed across 11 projects
Output
From feasibility to commissioning, built by youth, for their communities.
All projects at a glance
12 projects · updated Oct 2025
Project |
Location |
Cohort |
Type |
Capacity (kW) |
Annual kWh |
CO₂/yr (t) |
Status |
|---|---|---|---|---|---|---|---|
| NAIT | Edmonton, CA | 0 | Grid-tied | 11.88 | 17,011 | 10.55 | Operational |
| Shames Mountain | Terrace, BC | 1 | Off-grid | 3.00 | 3,226 | 0.09 | Operational |
| UofM | Winnipeg, CA | 1 | — | 2.18 | 3,117 | 0.09 | Operational |
| UofC | Calgary, CA | 1 | — | — | — | — | Stalled |
| Aylluq Qanchaynin | Amazon, PE | 1 | Off-grid | 1.10 | 1,549 | 0.54 | Operational |
| JKUAT | Juja, Kenya | 1 | Off-grid | 4.56 | 7,226 | 2.95 | Operational |
| Western U | London, CA | 1 | Off-grid | 1.60 | 2,087 | 0.08 | Operational |
| Spark Source | Ottawa, CA | 2 | Grid-tied | 4.95 | 6,744 | 0.26 | Operational |
| UofC Energy | Calgary, AB | 2 | Grid-tied | 7.20 | 10,819 | 5.30 | Installed |
| Western | St Thomas, ON | 2 | Grid-tied | 5.46 | 7,323 | 0.28 | Stalled |
| Luminosity Legends | Vancouver, BC | 2 | Off-grid | 1.46 | 1,806 | 0.03 | Operational |
| Solar EV | Winnipeg, MB | 2 | Off-grid | 2.18 | 3,117 | 0.004 | Operational |
| Total | 45.57 kW | 64,025 | 20.16 t | ||||
| Project | Capacity | Status |
|---|---|---|
| NAIT Cohort 0 |
11.88 kW |
Operational |
| Shames Mountain Cohort 1 |
3.00 kW |
Operational |
| UofM Cohort 1 |
2.18 kW |
Operational |
| UofC Cohort 1 |
— | Stalled |
| Aylluq Qanchaynin Cohort 1 |
1.10 kW |
Operational |
| JKUAT Cohort 1 |
4.56 kW |
Operational |
| Western U Cohort 1 |
1.60 kW |
Operational |
| Spark Source Cohort 2 |
4.95 kW |
Operational |
| UofC Energy Cohort 2 |
7.20 kW |
Installed |
| Western Cohort 2 |
5.46 kW |
Stalled |
| Luminosity Legends Cohort 2 |
1.46 kW |
Operational |
| Solar EV Cohort 2 |
2.18 kW |
Operational |
| Total | 45.57 kW |